I'm a Residential Customer
I'm a Business Customer
I'm a Contractor / Builder
find out more about Conservation
Sustainable Development
Environmental Management
find out more about Electricity Retailer
Please select an area below
Connect to Distribution
Generation Connection Process - Micro
Generation Connection Process - Small
Generation Connection Process - Mid-Sized and Large
Roles of Government Agencies and Organizations
Generation Capacity Limits
Residential/Business > Connecting Generation to Horizon's Distribution System

Connecting Generation to Horizon's Distribution System

Connecting Mid-sized and Large Generation to Horizon Utilities' Distribution System

The following is the process for connecting a mid-sized or large generation facility to Horizon Utilities' distribution system.

  1. Preliminary Assessment

    Note: This step is optional.

    In this step, the customer submits an Application for Preliminary Assessment (click here to download the application form).

    Horizon Utilities will meet with the customer to discuss the feasibility of the proposed generation connection.

  2. Connection Impact Assessment

    Note: Customers applying for a Feed-in Tariff contract from the Ontario Power Authority must enter into a Feed-in Tariff contract with the Ontario Power Authority before applying to Horizon Utilities for a Connection Impact Assessment. Click here to visit the Feed-in Tariff program website.


    To ensure the generation facility does not adversely impact its distribution system, Horizon Utilities must study the impact of the generation facility on its distribution system. The customer must submit an Application for Connection Impact Assessment (click here to download the application form).

    Horizon Utilities will perform a Connection Impact Assessment as long as the application is complete and meets the following requirements:
    • There is capacity available to accommodate the generation connection - click here for information on Horizon Utilities' generation capacity limits
    • The proposed in-service date is within 3 years (5 years for waterpower projects)

    The Connection Impact Assessment looks at impacts on power flow, feeder voltage, current loading, fault currents and power factor. Hydro One, the transmission company that owns the transformer stations to which Horizon Utilities' distribution system is connected, may also have to perform its own Connection Impact Assessment. For large generation facilities, the Independent Electricity System Operator will have to perform a System Impact Assessment.

    The customer must pay in advance for the cost of performing the Connection Impact Assessment.

  3. Offer to Connect

    If the customer is satisfied with the results of the Connection Impact Assessment and would like to proceed with the connection, Horizon Utilities will perform a cost estimate and present to the customer an Offer to Connect. The Offer to Connect will include the cost estimate, which specifies the expected costs of any modifications to Horizon Utilities' distribution system that are required to connect the generation facility.

    The customer must pay in advance for the cost of performing the cost estimate.

  4. Connection Cost Agreement

    Note: The Connection Cost Agreement is also known as the Capital Cost Recovery Agreement.

    If the customer accepts the Offer to Connect, the customer must enter into a Connection Cost Agreement with Horizon Utilities. The Connection Cost Agreement specifies the scope of work to be performed by either Horizon Utilities or the customer in order to make the generation connection, the costs associated with such work, the connection date, and any requirements that must be met.

  5. Design & Build

    Once the Connection Cost Agreement is executed and any required payments are made, Horizon Utilities will perform the work required to make the connection. The customer will submit final detailed design documents to Horizon Utilities for review. The customer will complete the construction of the generation facility.

  6. Connection Agreement

    Before the connection is made, the customer must enter into a Connection Agreement with Horizon Utilities. The Connection Agreement will detail any operating conditions and responsibilities.

  7. Connection

    Once testing and commissioning is completed, and Electrical Safety Authority (ESA) authorization is obtained, the connection of the generation facility to Horizon Utilities distribution system will be made.

<Go Back>

Privacy Policy Terms of Use

Copyright © 2008-2010 Horizon Utilities Corporation. All rights reserved.
® Registered Trademark of Horizon Holdings Inc.
OM Official Marks of the Ontario Power Authority. A mark of the Province of Ontario protected under Canadian trademark law. Used under sublicence

Some portions of this site require Macromedia Flash Player or Adobe Acrobat Reader. Bookmark and Share